Pre-commencement works on the Place House site have now been finalised. Ealing Council have also discharged the last pre-commencement planning condition which means that the demolition of the buildings and refurbishment of the Grade 2 listed Place House and Folly can start in earnest.

Bowmer + Kirkland are hoping to have plant and labour mobilised to start demolition work on Monday 18th March.

The areas for demolition and the phasing of the works can be seen on the diagram below (green designates the buildings which are being retained):

Queries regarding the site can contact Keith McGinness, Senior Project Manager for Bowmer + Kirkland (k.mcginness@bandk.co.uk) to receive regular bulletins on progress. His emergency contact number is 07827 987 501